The following is a list of current and past issues or projects
that the board is or has handled.
| Time Frame |
Issue |
Status Update |
Disposition |
| Winter 2009 |
Incorrect Roof |
Three new homes
in Southgate were approved with an incorrect three-tab shingles.
The decision was made to remove the shingles and replace them with
architectural shingles. |
The association paid $7,500 of
the replacement cost and the builder paid the remainder of the cost. |
| Winter 2009 |
Pool Repairs |
Pool plastering
is expected to occur on Dec 12th or 13th.

Pre-plastering of the pool |
The pool was re-plastered on Dec
12th and 13th. Photos of the refinishing process:

The pool has been re-filled and is ready for the 2010 season! |
| Winter 2008 |
Pool Shade Covers |
The pool shade
covers have been replaced due to hurricane damage. |
Shade covers have been replaced. |
| Fall 2009 |
Pool Furniture |
Due to ongoing
degradation of the pool chairs and lounges, the decision was to have the
current furniture repaired / re-strapped and the purchase of 6 new
lounges and 12 new chairs. |
Repairs have been approved. |
| Fall/Winter 2009 |
Evaluate the possible implementation of fine
structure for on-going violations |
The original fine policy filing
was discovered and will be implemented as filed. Residential
design guidelines will first be drafted and the program will be formally
mailed to homeowners as either part of the assessment or annual board
meeting mailing. |
A new guideline is expected be released in 2010 at the time
of the annual meeting. All home owners will receive a copy of this
new set of guidelines at the time when the fine policy is implemented. |
| Summer/Fall 2009 |
Sale and build out of the remaining ~35 lots in
Southgate and two lots in Crossgate |
Lakewood builder meet with the board during the
August board meeting to discuss approvals for three house plans that
currently do not meet standards. Two lots as of Aug 20th were
pre-sold and building should start in the September time frame.
The lots in Westgate will not be developed as part of this arrangement. |
Approval to start building on three of the Five-O lots
has been granted and will start very soon. The majority of plans
submitted have been approved. Three large square foot plans will
be voted on by home owners in Southgate section 11 and 12. As of
Dec 09, voting is being completed in southgate. |
| Summer 2009 |
Determine solution for dead trees on Assn and county
property. |
42 trees are marked for
removal. The county removed a number of trees that were located in the
county right-of-way saving the HOA potentially several hundred dollars
in removal costs. A final bid has been approved for the removal of the
remaining trees. |
Affected trees have been removed. It is
possible in the future that additional trees will be removed, along with
stump removal. |
| Spring/Summer 2009 |
Feb 2009 - Homeowners report ATV Traffic over Reserve C (pipeline easement) coming
through the neighborhood and over residents lawns. |
|
This project is now completed.
 |
| Winter/Spring 2009 |
Repairs to monuments and fences caused due to Sept
2008 hurricane. |
All repairs except for a small portion along the
Hardy toll road have been completed. |
Completed |